Bid Package Statuses

Within a Project, Bid Packages have two statuses: Enabled and Disabled. All newly created Bid Packages are created in the status of Enabled. A bid package will automatically become a Disabled 40 business days after the bid due date that is assigned to the Bid Package.


Manually toggling Bid Packages between Enable/Disable:

1. Navigate to the Bid Package


2. Select the Enable/Disable Bid Package button in the top ribbon


Enabled bid packages will be Disabled.


Disabled Bid Packages will be Enabled


Enabled Bid Packages


Disabled Bid Packages

  • Inaccessible to ALL listed Bidders in the Bidders by Division Grid.
    • Bid Package is removed from My Bid Packages for all listed Bidders.
    • Invitation to Bid hyperlinks are also disabled.
    • Bid Replies can no longer be updated.
  • Removed from the Public Bid Packages section of the login screen (if applicable)
  • Accessible by only Project Admins and Org Admins.

Additional Resources

Bid Packages

Bid Package Messages

The Bid Packages Report