The non-commitment cost column within a forecast worksheet is the value of the JTD Costs that are not associated with a Commitment. Typically, the non-commitment cost shows and costs to the cost code that have been applied in Sage 300 outside of the Commitment. 


If the non-commitment cost column within a Forecast is equal to the original Commitment, this means that the invoices are not being applied to the Commitment in Sage 300. 