Within the Cost Management, Summary Info page three gears are presented at the bottom of the page.  The gear represents three equations within your project cost management. 

 

Project Percent Complete

Amount of Budget Bought

Job to Date Percent of Estimate 

 

Hoover your mouse over each gear and the equation used to generate the amount represented will present in the tool tip.

 

Chart

Description automatically generated

 

 

 

Gear 1 - Project Percent Complete

Billed to Date/Total with Approved (Contract)

0.00 / 33,440 = 0 

 

Graphical user interface, application

Description automatically generated

 

A screenshot of a computer

Description automatically generated with low confidence

 

 

 

 

Gear 2: Amount of Budget Bought

Forecast Total Cost/(Estimate Original +Estimate Pending + Estimate Approved)

70,896.00 / (14,315 +37,690 + 4,900) = 1.2459 

 

Table

Description automatically generated

 

A screenshot of a computer

Description automatically generated with low confidence

 

 

 

Gear 3:  Job to Date Percent of Estimate 

Account JTD/Total with Approved (Estimate)

4,045.00 / (14,315 +4,900) = 0.2105 

 

Table

Description automatically generated

 

 

A screenshot of a computer

Description automatically generated with medium confidence