Use Forecasting Worksheets

 

  • You can create forecasting worksheets and enter work remaining to complete to track costs and evaluate remaining budget amounts. The system lets you create one worksheet per day. This job aid explains forecasting worksheets.

 

Create A Forecasting Worksheet

 

  • Go to Cost Management and select Forecasting - Variance

 

Cost Management 
Cost Management folder 
• Estimate Info 
• Pencil Draws 
• Contra& Info 
• Contra& Events 
• Commitrnent Info 
• Commitrnent Events 
• summary_lntg 
• Forecasting - Variance

 

  • The first worksheet of a project is the Initial Data Load. This is the data uploaded from Sage 300 Construction and Real Estate. If changes are made to estimates or commitments, you can click Refresh to update the worksheet.
    1. The first group of columns shows estimates and committed costs at the category level. Pending and approved changes are included, as well as job-to date costs
    2. The row at the bottom shows totals.
    3. Scroll to the right to see the Balance to Complete column

 

You are here: Home \ Cost Management 
72.00 
72.00 
10.00 
70.00 
805,921.61 78,409.25 
04,318.oc 85,142.00 
-114,479.2 
Select historical set to work with 
New Data Load (Dec 3 2019 ) 
Fo recast 
Summary 
New Worksheet 
Description 
New Data Load 
Copy Worksheet 
EXAMPLE 
Delete Worksheet 
Created by Sarah Clukey on Dec 3 2019 
Print Detail 
Save Changes 
Budget Values 
Extras Cost Code 
1-040 Coordination 
1-040 Coordination 
1-040 Coordination 
1-045 Insurance 
1-045 Insurance 
1-060 Reg. 
Requirements 
1-065 Permits - General 
1-510 Temporary 
Utilities 
1-510 Temporary 
Utilities 
1-510 Temporary 
Utilities 
1-510 Temporary 
Utilities 
1-580 Project 
Identification 
b 
Estimate 
a 
Balance To Complete C 
Original 
Original 
Units 
Units 
Original 
2,485.00 
84,638.52 
1,413.00 
0.00 
9,202.00 
5,606.00 
945.00 
2,700.00 
0.00 
0.00 
157.50 
Approved 
Change 
Orders 
3,340.00 
0.00 
6,175.00 
-650.00 
1,334.00 
200.00 
1,500.00 
5,400.00 
1,300.00 
250.00 
150.00 
250.00 
All 
Pending 
Chan 
4.00 
400.00 
12,000.00 
375.00 
100.00 
0.00 
0.00 
0.00 
0.00 
1,250.00 
0.00 
900.00 
94,696.25 
Total 
Units 
Total 
71.00 
0.00 
2,840.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
28,160.00 
35.00 
29.80 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
4,513.99 
Original 
Commi 
4,744.00 
5,000.00 
754.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
Pending 
Total 
Commitm 
Commi 
o 
Approved 
Commitm 
Chan 
301.00 
0.00 
0.00 
400.00 
0.00 
300.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
Non- 
Commitment 
0.00 
0.00 
28,000.00 
0.00 
0.00 
0.00 
5,606.00 
0.00 
0.00 
0.00 
0.00 
0.00 
33,381.00 
IDC k W O rksheet 
Actual 
Unit 
0.00 
0.00 
28.00 
0.00 
0.00 
0.00 
5,606.00 
0.00 
0.00 
0.00 
0.00 
0.00 
5,634.00 
Tota I Cost 
5,045.00 
33,000.00 
1,154.00 
0.00 
300.00 
5,606.00 
0.00 
0.00 
0.00 
0.00 
0.00 
328,458.25 
Balance To 
Complete 
Units 
1,843.00 
1.00 
0.00 
0.00 
1.00 
2.00 
0.00 
0.00 
1.00 
27,194.00 
Balance To 
Complete $ 
784.00 
400.00 
69,813.52 
-16.00 
1,434.00 
9,102.00 
1,500.00 
6,345.00 
4,000.00 
1,500.00 
150.00 
1,307.50 
650,568.86 
Forecast 
Units 
100. 
00 
75. 
00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
Unit 
Unit Cost 
Measu 
2,843.00 102,813.52 
0.00 
1.00 
1.00 
0.00 
1.00 
1.00 
2.00 
0.00 
0.00 
1.00 
5,829. 
00 
400.00 
1,138.00 
1,434.00 
9,402.00 
7,106.00 
6,345.00 
4,000.00 
1,500.00 
150.00 
1,307.50 
Chan 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
5,617.25 
5,045.00 
5,000.00 
1,154.00 
0.00 
300.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
295,077.25 
ea 
hrs 
Is 
40,000 
.00 
1,413.00 
9,202.00 
5,606.00 
945.00 
2,700.00 
157.50 
Foreca 
cost To 
Com lete 
1,000.00 
5,250.00 
40,000.00 
1,413.00 
0.00 
9,202.00 
5,606.00 
945.00 
2,700.00 
0.00 
0.00 
157.50 
765,048.0; 
Total 
Foreca 
Job Cost 
6,045.00 
5,250.00 
73,000.00 
2,567.00 
0.00 
9,502.00 
11,212.00 
945.00 
2,700.00 
0.00 
0.00 
157.50 
Foreca 
Variance 
-216.00 
4,850.00 
29,813.52 
1,429.00 
1,434.00 
-100.00 
4,106.00 
5,400.00 
1,300.00 
1,500.00 
150.00 
1,150.00 
Print sum. 
Actual % 
Complete 
86.55% 
0.00% 
32.100,4 
101.41% 
0.00% 
3.190,4 
78.89% 
0.00% 
0.00% 
0.00% 
0.00% 
0.00% 
28,195.00 
979,027.11

 

  • Enter values in the shaded columns, for Units, Unit of Measure, and Unit Cost.  When you change an amount, a red triangle appears in the top left of the cell. If you need to pause during data entry, click Save Changes

 

Save Changes 
Budget Va 
Extras Cost Co 
1-040 Coordinatio 
1-040 Coordination 
1-040 Coordination 
1-045 Insurance 
1-045 Insurance 
1-060 Reg. 
Requirements 
1-065 Permits - General 
1-510 Temporary 
Utilities 
1-510 Temporary 
Utilities 
1-510 Temporary 
Utilities 
1-510 Temporary 
Utilities 
1-580 Project 
Identification 
Fo recast 
Summary 
72.00 
72.00 
805,921.61 78,409.25 
New Worksheet 
Copy Worksheet 
Delete Worksheet 
Estimate 
Original 
Original 
Units 
Units 
Balance To Complete 
Original 
2,485.00 
84,638.52 
1,413.00 
0.00 
9,202.00 
5,606.00 
945.00 
2,700.00 
0.00 
0.00 
157.50 
Approved 
Change 
Orders 
3,340.00 
6,175.00 
-650.00 
1,334.00 
200.00 
1,500.00 
5,400.00 
1,300.00 
250.00 
150.00 
250.00 
All 
Pending 
Changes 
4.00 
400.00 
12,000.00 
375.00 
100.00 
0.00 
0.00 
0.00 
0.00 
1,250.00 
0.00 
900.00 
94,696.25 
Total 
Units 
Actual 
Unit 
Total 
Original 
Commi 
Approved 
Commitm 
Chan 
Pending 
Total 
Comm i tm 
Commi 
Chan 
o 
71.00 
2,840.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
28,160.00 
35.00 
0.00 
29.80 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
4,513.99 
4,744.00 
0.00 
5,000.00 
754.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
979,027.11 204,318.oc 85,142.00 
301.00 
0.00 
400.00 
0.00 
300.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
5,617.25 
5,045.00 
5,000.00 
1,154.00 
0.00 
300.00 
0.00 
0.00 
0.00 
0.00 
0.00 
0.00 
295,077.25 
Non- 
Commitment 
0.00 
28,000.00 
0.00 
0.00 
5,606.00 
0.00 
0.00 
0.00 
0.00 
0.00 
33,381.00 
0.00 
0.00 
28.00 
0.00 
0.00 
0.00 
5,606.00 
0.00 
0.00 
0.00 
0.00 
0.00 
5,634.00 
Total Cost 
5,045.00 
0.00 
33,000.00 
.00 
0.00 
300.00 
5,606.00 
0.00 
0.00 
0.00 
0.00 
0.00 
328,458.25 
Balance To 
Complete 
units 
0.00 
1.00 
0.00 
0.00 
2.00 
0.00 
0.00 
27,194.00 
Balance To 
Complete $ 
784. 
69,8 
-16. 
1,434. 
9,102. 
1,500. 
6,345. 
4,000. 
1,500. 
150. 
1,307. 
650,568.86 
Forecast 
Units 
100. 
00 
4 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
1.00 
Unit 
Measu 
ea 
hrs 
Is 
1.00 
1.00 
0.00 
1.00 
1.00 
2.00 
0.00 
0.00 
1.00 
28,195.00 
5,829. 
00 
400.00 
2,843.00 102,813.52 
1,138.00 
1,434.00 
9,402.00 
7,106.00 
6,345.00 
4,000.00 
1,500.00 
150.00 
1,307.50 
Print Del 
unit C 
40,000. 
1,413. 
9,202. 
5,606. 
945. 
2,700.

 

  • The forecasted variance is calculated using the formula shown below
    1. Risk is a percentage of risk against only the Forecasted Amount Remaining
    2. For categories against which a commitment for the full budgeted amount exists, any additional units are shown as negative forecasted variance-meaning the cost has exceeded the budget
    3. Total Estimate - (Forecasted Cost to Complete + Current Total Costs) = Forecasted Variance

 

Total Estimate Calc: 
Cabo Hilton Project 
Forecasting worksheet 
Select 
Project Forecasting 
Total Commitment Calc: 
Initial Data Load 
Forecasted Job Cost: 
Balance to Complete Calc: 
Forecast Risk Variance: 
D-S=T 
Forecasted CTC: 
L.st sy€d 
To Excel Refresh 
Forecasted Variance: 
D-O=p 
Copy vvo" Lock w." 
e save Chan.es 
New Worksheet 
Budget Values: 
Pulled from the 
budget, to the 
category 
Estimate 
02-140 
Costs: 
The Commitment 
Values and 
Associated Cost 
Events from SCPC 
JTD costs: 
Sage 300 Costs less 
the Released SCPC 
Costs 
u 
Appvd 
Chg. 
Risk Input Field (%) 
Forecast Input Fields 
Revenue: 
The Approved and 
Pending Change 
Events from SCPC 
Summa ry 
Cost COO 
estimate Chang" 
$12,500.00 
S21S.".CO SC_OO 
SO.OO SO.OO 
Forecast Calculated Fields 
Forecasted Job Cost with Risk: 
S 14'.#.00

 

Copy A Worksheet to Update Information

 

  • At any point after the day of the initial data load, click Copy Worksheet to start a new worksheet with the data you have already entered.

***NOTE: If you click New Worksheet, any values in the units columns are not copied***

In this example, your original estimate for cost code 3-310 L was for 64 hours at $80/hour ($5,120). However, now you’ve concluded that you’ll need 80 hours of labor, plus or minus 10%

 

  • Enter the new forecasted numbers and risk

 

Mew 
1 
h3noes 
Budset 
3-2:0 
3-320 
3-320 
3-343 
3-345 
3-360 
3-270 
3-270 
2„110 
2-410 
Works heet 
120.00 
$4, 
±8Υ.Ζ0 
$5, 
220.10 
$75, 
$3,εοο αο 
$3, 
225.10 
$3, 
αοο.αο 
$5, 
760.10 
$1, 
920.10 
$125.10 
$2,αοο.αο 
$5,7ςο.αο 
Delete 
W orksheet 
80 
$0,00 
$0,00 
$0,00 
$0,00 
$0,00 
$0,00 
$0,00 
$0,00 
$0,00 
ςο.οο 
ςο.οο 
Το 
$0.οο 
$1.00 
$1.00 
*α.οο 
εα.οο 
*α.οο 
$9,830.οο 
$o.co 
$o.co 
$o.co 
$o.co 
$0.αο 
$0.αο 
$0.αο 
$0.αο 
$0.αο 
$0.αο 
$0.αο 
$0.αο 
$ 3,800. οο 
33,325.οο 
33,000.οο 
35,760.οο 
31,920.οο 
$925. οο 
$2,οοο.οο 
45,760.οο 
$2,οοη.οο 
0,002', 
0,002', 
ο.οοψ, 
$0.οο 
$0.αο 
$o.co 
$o.co 
$o.co 
$0.αο 
$o.co 
$o.co 
30.10 
$o.co 
*0.10 
*0.10 
$4,38' 
$5,120 
$75,33 
33,325 
$5,760 
$1,320 
$225 
'5,760

 

  • Click Lock Worksheet when you have finished entering data. At that point, you’ll be able to view a PDF of the worksheet, and the Delete Worksheet button will be unavailable.

 

  • When you save changes to the worksheet, the Forecasted Cost to Complete reflects your new estimate, and the Forecasted Job Cost with Risk is: (Cost) * (Risk) = Forecasted Risk $6,400 * 1.1 = $7,040.00

 

Save * 
hanoes 
Ri5k 
вј.оо 
Worksh 
соџу 
го 
$1',sy.J0 
$з,воо.оо 
Worksheet 
Ехџоп то 
Со mp'ete 
3-250 
3-310 
3-310 
3-34' 
$Ј.со 
*Ј.со 
$Ј.со 
$о.со 
Со 
4 
$€,чш.јо 
stg 
$о.оо 
$€,чоо.оо 
$о.оо 
$4, 
981.50 
авс.оо 
s:s.oo 
$з,Еос оо 
0.0 оте 
0.00',е 
0.0 оте 
0.00',t 
0.00',t 
0.00 % 
witf 
$с.оо 
$1,Lqc.oo 
$с.оо 
$о.оо 
-$l,S2J.co 
$1',S'3.co 
$з,ьоо.со

 

 


Published:12-2019 | Revised:03-2020 v