BASICS 

The Submittal Package contains Submittal Items.  It is the items within each package that contain the item status.  This will allow for each item to maintain its own status, the package will not maintain a status. 

 

Organizing your Submittals 

For most projects it will be most efficient to Create the Submittal Packages in the primary Submittal Module without a sub-folder structure. For more complex projects advanced options using sub-folders is available.  

 

Submittal Project Defaults

To better understand how you can define your defaults please see 1.5 Project Defaults

 

Ball in Court (BIC) 

There are four stages of the submittal which determine the BIC (Stage --> BIC) 

  1. Created --> Project Manager Company 
  2. Submitted --> Reviewing Company
  3. Returned 
    1. Approved Statuses --> None 
    2. Revise and Resubmit --> Submitting Company
    3. Rejected Statuses --> Submitting Company
  4. Complete --> None 

 

Submittal Report

To better understand how create and distribute the Project Submittal Reports please see 5.1 Project Reports 

 

CREATING A SUBMITTAL PACKAGE 

 

General Overview of the Submittal Package 

 A submittal package in the system is created to hold items for review. You can create one package per item or include many items per package, the steps will be the exact same. 

 

Create the Submittal Package 

Navigate to the Project Management Module and click the Submittals Link.

 

Machine generated alternative text:
Project Management 
Project Management folder for project 'SJC Testing Grounds' 
• Communications 
• Submittals 
• Transmittals 
• Expediting Logs 
• Punch Lists 
• Issues 
• Meetings 
• Time Tracking

 

Within the Submittal module, click on New Package in the upper Left.

 

Machine generated alternative text:
You are here: Home \ Project Management 
Home Print/ Reports 
New Folder New Package 
Create New

 

Fill in the required information with the asterisk next to it and include a submitting Subcontractor if that makes sense for the project. (Subcontractor will need to be a project member) Click Save.

 

Machine generated alternative text:
You are here: Home \ Project Management \ Submittals 
Create New Submittal Package 
Submittal Package Information 
Number * 
03-3100 
Description * 
Mixed Concrete 
Reviewing Company * 
Project Sample, Architect (Arch) 
Project Manager * 
Project Sample, General Contractor (Printer) 
Submitting Company 
Project Sample, Subcontractor (Sub) 
Notes 
Pending 
SAVE 
SAVE & NEW 
SAVE & COPY 
CANCEL

 

Create Submittal Items 

 Below the Submittal Package Information click Add Submittal Item and fill in the required information.

 

Submittal Package Information 
Subject Test Package 
To: Sample Owner 
From: Alotof Paperclips 
Submitting Contact: 
Submittal Items 
o 
Number 
No records to display. 
Attach 
Revison 
Status 
Stage 
Next Action 
EDIT 
Su bject 
Type 
CSI 
Division 
Page size: 
20 
ADD SUBMITTAL ITEM 
Responsible 
Due Date 
Contractor 
0 items in 1 pages

 

The Item Type can be customized in the List Management for the Org or Project. Under the Tracking Information keep the Dates Blank since they will be automatically filled in after saving.

 

**NOTE: If the Supporting Documents are saved to the Item, the reviewing company will need to login to the site to view the item and the attachments. It is recommended that the files are attached at the package, this will allow the reviewing company to view the attachments from the email**

Machine generated alternative text:
Create New Submittal Item 
Item Information 
Number * 
000001 
Description * 
Mix Concrete 
Copies Submitted * 
Revision 
0000 
Item Type 
Product Data 
CSI Division 
03000 (Concrete) 
Tracking Information 
Submittal Review Time * 
Date Required from Review 
Item Status * 
For Approval 
Responsible Contractor 
Mark as 'Closed' 
Project Sample, Subcontractor (Sub) 
Date Received from Subcontractor (This dare 
Date Returned to Subcontractor 
is i+rrnaCiU7 and be manually)

 

Click Save & View Package if you are done

Click Save & New to save the current item and create a new one from scratch 

Click Save & Copy to save the current item and create a new item with the current data

 

Machine generated alternative text:
SAVE & VIEW PACKAGE 
SAVE & NEW 
SAVE & copy 
CANCEL

 

Upload Supporting Documents 

 

Adding Attached Documents

  1. Within the submittal Package, navigate to the bottom to the Attachment area. 
  2. Drag and drop into the dark grey area or click Browse file(s) to find the items you want to attach.
  3. Enter the File Description above the dark grey area with a description such as Initial For Review.
  4. Click Upload Files.

 

Attached Document Folders 
No records were found. 
Attached Document References 
No records were found. 
File U load 
Enter file(s) description here 
Browse file(s) 
Drag and drop files here 
Drag and Drop a file here. 
Upon selection, please wait until your files have 
been completely uploaded before saving. 
UPLOAD FILE(S) 
nly PDFs combine in Print and Downloads 
CANCEL

 

Adding Referenced Documents 

    Files will need to be uploaded to the project within the project documents section.  See Uploading Documents 

    Within the Submittal Package, top ribbon bar, select File Attachments, Reference Documents 

Machine generated alternative text:
You are here: Home \ Project Management \ Submittals 
File Attachments Print/ Reports 
Home BIM 
Add File 
Add Multiple Files 
Reference Documents 
Attachment Options

    Navigate to the location of the files/folder.  Check the box before the file/folder and scroll to the bottom and click Attach

Machine generated alternative text:
Documents 
General & Photos > FOLDER 
Move To 
Delete Selected Documents 
Document 
AOI Symbols and Abbreviations 
Z] A02 Finish Schedule Partition Types 
A02 REVI Symbols and Abbreviations (2) 
[Z A03 Door Schedule and Details 
A03 REVI Door Schedule and Details 
c 
AIOI Men's Locker Room Lounge 
< < 1 Page size: 100 
Title 
AOI Symbols and Abbreviations 
A02 Finish Schedule Partition Types 
A02 REVI Symbols and Abbreviations (2) 
A03 Door Schedule and Details 
A03 REVI Door Schedule and Details 
AIOI Men's Locker Room Lounge 
Sketch 
Download Discipline 
Architectural 
Architectural 
Architectural 
Architectural 
Architectural 
Architectural 
Listed Project Members are notified when Documents are Uploaded/updated. 
Folder Reviewers 
Delete Selected Follower(s) 
Reviewer Name 
Sarah, Clukey 
Support, Stratusvue 
< < 1 Page size: 
100 
Attach 
Cancel

 

    The file/folder will show as a referenced file/folder to the Submittal Package.

 

 

Create Submittal Package Transmittal 

You can choose to send one or all submittal items within the Submittal Package. Anything that you want to send at this time must be selected by checking the box next to that item. This includes the Submittals item(s) and any submittal package attachments, referenced documents, and/or referenced folders. 

 


Click all of the Submittal Items and documents you wish to send. Click on the Submit For Review Button at the top.

 

**Note: If you have more than 10 items use the Page Size drop-down at the bottom of the grid to display all your items that should be sent.** 

Home BIM 
File Attachments 
Print / Reports 
e 
Submit For Review Return From Review Create Item Revision 
Send Options 
Submitting Contact: 
Submittal Items 
Return To sub 
Forward Expediting Link 
Options 
o 
o 
Number 
000001 
Attach 
Revison 
0000 
Status 
For Approval 
Stage 
Created 
Next Action 
Submit for 
Review 
Su bject 
test package-product Samples 
Type 
Product Samples 
CSI 
Division 
Page size: 
20 
ADD SUBMITTAL ITEM 
Responsible 
Due Date 
Contractor 
1 items in 1 pages

 

Transmitting the Transmittal 

When the transmittal is created the required fields are the To and From fields. 

To and From are defined by Submittal Package Information, located within the Submittal Package.  However the To and From can be modified to be different project members.

Machine generated alternative text:
40520-004-002 
Submittal Package Information 
Subject 40520 (Masonry Anchorage Reinforcing and Accessories) 
To: Architect Sample 
From: Support Stratusvue 
Submitting Company: Ernie Electrician 
EDIT

Additional information that can be added to the transmittal:

    Remarks can be used to personalize the emailed Transmittal 

    Items being sent will include quantity and description of physical objects that may be delivered outside of the electronic          transmittal.

    CC Users if needed (If a Contact is selected they do not receive an email).  Click on the blue plus and select the project             members to be included on the transmittal.

    Send the Transmittal by clicking on Transmit within the top ribbon bar. 

 

Home 
Paste 
Delete 
Print 
Add File 
Add Multiple Files 
Transmit Forward 
Fax 
Edit Options 
Reference Documents 
Attachment Options 
Send Options




 

CREATE A SUBMITTAL ITEM REVISION 

 

Navigate to the Project Management Module and click the Submittals Link 

Open the Submittal Package  

Select the one or many Submittal Items to revised by clicking on the checkbox to the left 

Click on the Create Item Revision button at the top 

The Submittal Item stage will be updated to that status of Complete. A newly created Submittal Item with the same item number will be shown with a revision number.